Road Projects Progressing In Village Of Milford
September 23, 2019
A road construction project is continuing in the Village of Milford, while a separate paving project is now largely wrapped up.
The South Milford Road project is progressing along with the paving of Stage 1 of the project taking place Friday. Work will continue this week with electrical work and concrete repairs. Officials advise that the traffic switch for Stage 2 of the project is anticipated to occur later in the week with milling and concrete curb installation to follow.
Meanwhile, the Village says the 2019 Paving Program largely wrapped up with the paving of East Commerce Road late last week. Clean-up and restoration work got underway on Friday and officials say there are some remaining minor punch list and cleanup items that will be continuing this week. (JM)